Installation work at the construction site of the Kochubeevskaya wind farm began in April 2020. This wind farm is located in the Kochubeevsky district of the Stavropol Territory.
The site has 84 wind turbines with a capacity of 2.5 MW each, the total capacity of the wind farm is 210 MW, which makes it the largest operating wind farm in Russia today.
The height of the wind turbine at the Kochubeevskaya wind farm (together with the rotor) is 150 m. The length of the blades is 50 m, and the weight of each is 8.6 tons. The tower itself weighs about 200 tons, the generator - 52 tons. The total weight of the structure is approximately 320 tons.