Berestovskaya wind farm is located on the territory of the Petrovsky district of the Stavropol Territory, which is now a key region for the implementation of wind energy projects of NovaWind JSC.
The installed capacity of the wind farm is 60 MW. The site has 24 wind turbines with a capacity of 2.5 MW each. The planned average annual energy production is 175.5 million kWh.
The height of the wind turbine at the Berestovskaya wind farm (together with the rotor) is 150 m. The length of the blades is 50 m, and the weight of each is 8.6 tons. The tower itself weighs about 200 tons, the generator - 52 tons. The total weight of the structure is approximately 320 tons.